STATUS


Main Components Need ( 1 tower) Have  
PMTs (15") 168 248  
Benthos spheres 268 450  
Mechanics (floors) 12 8 (3 Al & 5 Ti *)  * 3 of the Ti built in Pylos
Electronics
(floors module)
12 Production
phase
 
ElectroOptical
cable to shore
18 fibers + 1 conductor
1 Will be
rectified by
Autumn 2001
 
 3 DUMAND STRINGS INCLUDING "CHIRPED SONAR"
+
i.e. POSITIONING < A FEW cms